I just completed a full Oil & Gas project schedule in Primavera P6 Professional, built from scratch as part of my ongoing learning in project controls.
Here's what the schedule includes:
- Full WBS structure across 6 phases; Initiation, Engineering, Procurement, Construction, Testing & Commissioning, and Handover
- 25+ activities with realistic durations and Finish-to-Start predecessor logic
- 6 resources assigned across all phases; Project Manager, Lead Engineer, Procurement Officer, Site Supervisor, HSE Officer, and Construction Crew
- Cost loading of $1.6M across all activities with expense categories
- S-Curve generated showing cumulative budget distribution
- Baseline locked and constraints applied showing critical path analysis
- Project duration: 12 months (Feb 2024 - May 2025) - Total budget: $1,628,000 - Critical path identified with -53d float , showing real schedule pressure
Post image
Post image
Back to feed
The network for creativity
Join 1.25M professional creatives like you
Connect with clients, get discovered, and run your business 100% commission-free
Creatives on Contra have earned over $150M and we are just getting started